Gas Pipelines

COMPLETED PROJECTS

NAME OF WORK
MDPE Laying ,Last mile connectivity ,Liasioning & Associated works at Indore,Ujjain & Gwalior CGD Project for Aavantika Gas Limited
CLIENT
Aavantika Gas Limited
DESCRIPTION OF WORK
MDPE Pipeline
AMOUNT (CRORES)
4.2 Cr
COMPLETION YEAR
2017
NAME OF WORK
Laying of MDPE Network ,PNG Connection and Associatied works for Ujjain City Gas Distribution Project ( Azad Nagar)
CLIENT
Aavantika Gas Limited
DESCRIPTION OF WORK
MDPE Pipeline
AMOUNT (CRORES)
2.9 Cr
COMPLETION YEAR
2016
NAME OF WORK
Laying of MDPE Network and Associated works for indore City Gas Distribution project. (Musakhedi)
CLIENT
Aavantika Gas Limited
DESCRIPTION OF WORK
MDPE Pipeline
AMOUNT (CRORES)
2.3 Cr
COMPLETION YEAR
2016
NAME OF WORK
MDPE Laying & Liaisoning work from MR-10 to luv kush square indore.
CLIENT
Aavantika Gas Limited
DESCRIPTION OF WORK
MDPE Pipeline
AMOUNT (CRORES)
1.1 Cr
COMPLETION YEAR
2016
NAME OF WORK
Supply,Fabricarion,Erection and Testing of Pipe Laying and Associated Work for City Gas Distribution Project in Ujjain ( For Part B )
CLIENT
Aavantika Gas Limited
DESCRIPTION OF WORK
Steel Pipeline
AMOUNT (CRORES)
6.1 Cr
COMPLETION YEAR
2016
NAME OF WORK
Annual Rate Contract for laying and construction of 6"NB X 12 Km & 4"NB X 1Km Underground Steel Pipeline Network & Associated Works in Pune, Pimpri-Chichwad,Chakan,Talegaon & Hinjewadi for City Gas Distribution Network of MNGL,Pune
CLIENT
MNGL
DESCRIPTION OF WORK
Steel Pipeline
AMOUNT (CRORES)
3.7 Cr
COMPLETION YEAR
2016
NAME OF WORK
Laying & Construction of 10" NB X 4.7KM & 4"NB X 2 KM Underground Steel Pipeline Network & Associated Works from Rajaram Bridge to Mukund Nagar in Pune City For City Gas Distribution Network of MNGL,Pune
CLIENT
MNGL
DESCRIPTION OF WORK
Steel Pipeline
AMOUNT (CRORES)
3 Cr
COMPLETION YEAR
2016
NAME OF WORK
Laying & Construction of 10" NB X 7.5 KM Underground Steel Pipeline Network & Associated Works from Yerwada to Chandannagar in Pune City For City Gas Distribution Network of MNGL,Pune
CLIENT
MNGL
DESCRIPTION OF WORK
Steel Pipeline
AMOUNT (CRORES)
5.5 Cr
COMPLETION YEAR
2016
NAME OF WORK
Annual Rate contract for construction of pipeline & associated facilities for supplying gas to consumers in Bhiwadi /Neemrana/ Kushkhera region of Rajasthan.
CLIENT
Gail India Limited
DESCRIPTION OF WORK
Construction of Pipeline
AMOUNT (CRORES)
4.6 Cr
COMPLETION YEAR
2015
NAME OF WORK
Composite Construction Work (Comprising of Civil, Mechanical Electrical Works) at CNG mother station at Ujjain
CLIENT
Aavantika Gas Limited
DESCRIPTION OF WORK
CNG Station Work
AMOUNT (CRORES)
4.7 Cr
COMPLETION YEAR
2015
NAME OF WORK
Annual Rate contract for construction of pipeline & associated facilities for supplying gas to consumers in Bhiwadi /Neemrana/ Kushkhera region of Rajasthan.
CLIENT
Gail India Limited
DESCRIPTION OF WORK
Construction of Pipeline
AMOUNT (CRORES)
₹5 Cr
COMPLETION YEAR
2015